60,000 m² floor for a new storage hotel on the outskirts of Paris. This was the task faced by fibo intercon’s client, whose company is based in Luxemburg. The project, however, was associated with logistical difficulties. First and foremost the concrete had to be delivered con - tinuous ly which according to calculations required 10 truck mixers each day to go back and forth between the concrete factory and the construction site. Another challenge was the traffic difficulties which frequently arise in and around the French capital. Delays in concrete deliveries could put the project time schedule at risk and ultimately lead to daily fines for the contractor. Thus, great risk was associated with having a concrete factory supply concrete for the project. Therefore fibo intercon’s customer started looking for other solutions.