GVG Industrie-Bodenbau GmbH concreted a jointless industrial floor slab with an area of 7500 m2 within one day. The special concrete for floors from Cemex Deutschland AG made the extraordinarily high installation rate possible. The building company installed 1721 m3 of aaton floor in the floor slab in fifteen hours. The daily output was also so high because the factory-mixed aaton floor does not require the addition of a liquefier on site, which saves time.