An approximately 64 m long 3-section bridge, comprised of prestressed concrete T-beams on cast-in-situ concrete piers and abutments, is being built in East Germany. The structure is founded on precast steel-reinforced concrete ‘Centrum system’ piles. A total of 120 piles, measuring 40 x 40 cm in lengths from 20 to 27 m, were installed.