Bridge construction on 120 precaststeel-reinforced concrete piles

Precast steel-reinforced concrete piles as an ideal foundation system

An approximately 64 m long 3-section bridge, comprised of prestressed concrete T-beams on cast-in-situ concrete piers and abutments, is being built in East Germany. The structure is founded on precast steel-reinforced concrete ‘Centrum system’ piles. A total of 120 piles, measuring 40 x 40 cm in lengths from 20 to 27 m, were installed.

Subscribe to magazine

Contact

CentrumPfähle GmbH Herr Wardinghus Friedrich-Ebert-Damm 111 22047 Hamburg, GERMANY T +49 40 696720 F +49 40 69672222 www.centrum.de info@centrum.de

Events

06.08.2024 - 08.08.2024
14.08.2024 - 16.08.2024
21.08.2024 - 24.08.2024