50 hours under water

Putzmeister Concrete Pumps GmbH, 72631 Aichtal, Germany

Directly on the banks of the Danube, the city of Linz is expanding the ARS Electronica Center, also known as the "Museum of the Future" with a new building. The construction work on the project began in spring 2007 and completion is planned for the end of 2008. For the seamless production of a 40 x 90 m underwater concrete base plate, the largest truck-mounted concrete pump in Austria, a Putzmeister BSF 63- 5.20 H, delivered 3,300 m³ of concrete without interruption. Divers assisted at the job which took two days.